Staff reports 20–24 week lead time for Johnson Controls HVAC units; negotiated 25% down payment of $610,040

Portage County Board of Commissioners · November 7, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Portage County staff told commissioners the juvenile-detention center HVAC replacement with Johnson Controls carries lead times of 20–24 weeks; installation phases could take up to two weeks per unit and the county negotiated a reduced down payment of 25%, quoted at $610,040, with phased ordering.

Portage County staff provided a detailed procurement update on HVAC replacements planned for the juvenile-detention center (JDC). Staff summarized lead times and contract terms provided by Johnson Controls and described next steps for ordering, legal review and phased installation.

Staff said Johnson Controls reported average lead times of 20 to 24 weeks from order to on-site delivery for current units, with actual install-to-complete…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans