Burleson ISD opens community clinic; Mound Elementary gym addition progresses on schedule

Burleson Independent School District Board of Trustees · November 5, 2025

Get AI-powered insights, summaries, and transcripts

Subscribe
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The district reported the Texas Health Medical Associates clinic at the Chamber Building opened in September and construction of a full-size gym at Mound Elementary is underway with an expected early-spring completion; the Mound project includes an ICF storm-shelter component and is tracking under budget.

District staff provided updates on two facilities projects at the Oct. 27 board meeting.

Tyler Boswell said the Texas Health Medical Associates clinic, renovated from an existing Chamber Building, completed closeout in August and opened as a health clinic and sports medicine site on Sept. 2. The renovation included new plumbing, ADA pathways, exam rooms, a lab and x-ray room, and in-house cabinetry produced by district maintenance staff.

Boswell also reported on the Mound Elementary gym addition. The project adds about 9,400 square feet, includes insulated concrete form (ICF) walls that serve as a storm shelter, required 28 foundation piers, and has major mechanical equipment and roof work underway. He said masonry and other interior work are in progress and the project is tracking to an early-spring completion; the district reported the project remains under budget.

Board members and campus staff praised the improvements; several trustees and the principal said parents and students have reacted positively to the new windows and gym progress.