Seward connection work creates $140,000 change order; school bond to cover cost, buses rerouted during work
Summary
Contractors found an unmarked Verizon line while trenching on the Seward connection, producing an estimated $140,000 change order paid from the school bond; meanwhile, Reservoir Road construction will force temporary bus-route changes and a planned dry run with parents and police.
Contractors on the Seward connection project uncovered an unmarked Verizon line during excavation, forcing a trench bypass and producing a change order now estimated at roughly $140,000, committee members said. The work and associated change orders will be paid from the school bond, and staff reported the project is otherwise progressing…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat