Bluff council approves $1,950 design addition for Cooperative Cultural Center HVAC
Summary
By unanimous vote, the Bluff Town Council approved a $1,950 invoice and contract amendment with Uncommon Architects to add commercial ventilation/HVAC design to the Cooperative Cultural Center auditorium and kitchen after staff said the work was missed in earlier plans and a larger estimate was negotiated down.
Get email alerts on the Facility Maintenance topic
No spam. Unsubscribe anytime.
The Bluff Town Council voted unanimously Nov. 4 to approve a $1,950 invoice from Uncommon Architects for additional design work adding commercial-grade ventilation and HVAC to the Cooperative Cultural Center auditorium and kitchen.
Town staff told council members that the HVAC work was not included in earlier drawings and came to light during the project walk-through. Malia Collins, a town staff member, said the fee had been negotiated down from higher estimates: "I reached back out to Michelle of Uncommon Architects, and I said, what? And she said, actually, I brought this down from $10,000 from the, Resolute Engineering Group. ... she actually got it down to 1,950," Collins said during the meeting.
Staff and council members said paying for the design change now would likely be far cheaper than addressing a missing HVAC system with a construction change order later. The $1,950 adjustment was described as a modest addition to the overall project budget for a contract described in the meeting as roughly $176,000 in total value.
Motion language recorded in the public meeting was: "Motion to approve Uncommon Architects invoice and bid of $1,950 for design additions at the Cooperative Cultural Center." The motion passed by voice vote; meeting minutes record the outcome as unanimous (5–0).
The council did not specify follow-up procurement steps at the meeting; staff indicated the amendment would be ratified in contract records and the design work would proceed to incorporate commercial ventilation into kitchen and auditorium drawings.