Keats roadway project bidding delayed while USDA review and remaining easements are resolved
Summary
County planning staff said Nov. 6 that the Keats project cannot proceed to bid until outstanding temporary easements are secured and USDA confirms whether bidding may proceed during a federal shutdown. KDHE has approved plans; staff and BG are finalizing design and outreach.
Riley County planning staff updated the commission Nov. 6 on the Keats roadway project, saying engineering and bidding documents are ready but the project cannot go to bid until remaining easements are secured and USDA provides guidance.
Amanda Webb, planning director, told commissioners the county had 11 temporary easements and one permanent…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat