Clearlake delays award of Burns Valley/Olympic/Arrowhead repaving contract after tribal objections and litigation
Summary
City staff asked the council Nov. 6 to delay awarding the Burns Valley/Arrowhead/Olympic Drive repaving contract until state sign-off, saying the current scope is repaving only and that archaeological concerns relate chiefly to subsurface work removed from this scope.
City staff updated the Clearlake City Council Nov. 6 on the Burns Valley/Arrowhead/Olympic Drive pavement project and asked the council to delay awarding the construction contract until state authorization is received. Staff said the project scope is repaving only and does not include subsurface work such as trenches, vaults or culverts.
A staff presenter responded to a letter from the Koi Nation and noted that the nation had filed a lawsuit challenging the city’s environmental review for this project; staff said that lawsuit was dismissed by a judge for lack of merit. Staff also summarized the…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat