Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Right Of Way Acquisition topic

No spam. Unsubscribe anytime.

Public Works requests authorization to begin right-of-way acquisition for Lumpkin Campground Road/SR 53 intersection

Dawson County Board of Commissioners · November 7, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Public Works director asked commissioners to authorize right-of-way acquisition and budget estimate for intersection improvements at Lumpkin Campground Road and State Route 53, noting about 11 parcels affected and construction plans roughly 90% complete.

Public Works Director Robert presented an estimate and requested board authorization on Nov. 6 to begin right-of-way acquisition and related actions for the Lumpkin Campground Road at State Route 53 intersection improvement project.

Robert said BM&K had prepared right-of-way cost estimates and that the project will require a mix of fee-simple acquisitions, permanent easements and temporary easements across approximately 11 parcels. He told commissioners that construction plans are roughly 90% complete but that the plans must be finalized in coordination with utility companies and that final right-of-way needs may change as utilities and other conditions are resolved.

Robert described components included in the estimate such as costs for signs and other damages and said the estimate includes a contingency. He asked the board to authorize the acquisition process and the budget set forth in the estimate so staff can proceed with owner contacts and acquisition negotiations.

Commissioners expressed support for moving the project forward. No roll-call vote was recorded in the work-session transcript; staff requested formal authorization to proceed.