West Walnut redevelopment nearly complete; public works director says project will finish under budget after four‑year schedule
Summary
Public Works Director Jason Miles told the commission the West Walnut redevelopment project — originally planned for 24 months but extended to roughly four years due to unforeseen conditions — has finished major construction elements and is expected to come in under the original $40 million budget.
Public Works Director Jason Miles updated the Johnson City Board on the West Walnut redevelopment final balance change order and project status at the Nov. 6 meeting.
Miles said the project was originally estimated at 24 months but took about four years to complete due to unforeseen conditions encountered while replacing century‑old…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat