MidAmerican: turbines topped off, most circuits to be energized this week; transformer delayed
Page County Board of Supervisors · November 6, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.
Summary
MidAmerican Energy told Page County officials that all turbines for the local project are topped off, three of ten circuits are energized and six are expected by week’s end; the substation transformer remains delayed in transit with a November schedule.
A MidAmerican Energy representative told Page County supervisors the county wind project is nearing completion: every turbine has been installed and the project is moving toward full energization.
John from MidAmerican reported that “every turbine in the entire project is topped off” and…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans