Public works: Cass Park near completion; animal shelter opening delayed by railroad/Rhode Island Energy easement
Summary
Public Works Director Steven D'Agostino reported Cass Park is roughly 98% complete with a remaining payment and warranty/maintenance provisions; the new animal shelter hopes to open by month's end, but permanent power awaits a railroad-Rhode Island Energy easement.
Public Works Director Steven D'Agostino told the council the Cass Park project is nearly complete and that the city has equipment and maintenance plans in place for the new synthetic turf field.
"That project's pretty much done," D'Agostino said, estimating the project at about 98% complete and noting a remaining payment of about $600,000 that includes…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat