GIAA outlines $118.4M in capital works; apron, loading bridges and noise program prioritized

Guam Legislature Committee on Transportation, Tourism, Customs, Utilities, and Federal & Foreign Affairs · November 10, 2025

Get AI-powered insights, summaries, and transcripts

Subscribe
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

GIAA presented a portfolio of 17 ongoing projects totaling $118.4 million (about 84% federally funded) intended to repair typhoon damage, modernize the terminal and prepare for increased traffic; senators pressed timelines for loading-bridge replacements, apron rehabilitation, roof work and the FAA noise-compatibility program.

Frank Santos, a consultant to GIAA, told the committee on Nov. 10 that the airport has 17 active capital projects totaling $118,400,000, of which approximately $102,000,000 (84%) is federally funded and about $16,000,000 is the airport—s share.

Major work in progress includes terminal floor replacement (customs area terrazzo ~45–55% complete), HVAC upgrades in leased east operations, a $34 million apron rehabilitation project (about one-third complete), roof replacement (contracts executed; building permits pending and notice to proceed expected in December) and replacement of five loading bridges in an active procurement/contract-execution queue. Santos said the airport has 17 boarding bridges total and that procurement includes ground-power and preconditioned-air infrastructure for each bridge.

Noise compatibility and soundproofing: Santos outlined an updated Part 150/Part 150/115 noise exposure map that was submitted and approved by the FAA; a public hearing for the noise compatibility program concluded and a 30-day comment period is under way. GIAA has previously completed soundproofing for 250 homes and is working with FAA to design the next round of home sound treatments.

Other projects: planning and design studies include a microgrid study for airport power resilience (coordinated with Guam Power Authority and anticipated rooftop solar), bids are open for zero-emission vehicles and ground-support infrastructure, and an elevator/escalator (conveyance) modernization program is planned for FY26.

Why it matters: Senators asked whether the airport has sufficient operational capacity and maintenance to handle a passenger surge if incentives and marketing succeed. Management said many upgrades are recovery repairs from Typhoon Mawar but emphasized a cash constraint that limits the speed of work; the short-term credit facility and federal grants are intended to avoid halting critical work.

Provenance: Capital projects overview and project list were presented beginning at 00:34:07 and project details and timelines were discussed through 00:41:09.