Change order adds $38,459 and 63 days to Turkey Mountain parking-lot contract for rebar
Summary
City staff described change order No. 1 to TriStar Construction contract 137758 for Turkey Mountain parking lots, adding $38,459.02 (about 2.92% of the contract) and 63 calendar days to install reinforcement steel for the east and west lots. Staff recommended approval; the transcript records discussion but no recorded vote.
Get email alerts on the Turkey Mountain Change Order topic
No spam. Unsubscribe anytime.
Public Works staff presented change order No. 1 to contract 137758 with TriStar Construction LLC for project No. 2159FR0315, which adds $38,459.02 and 63 calendar days to the contract to install reinforcement steel (rebar) at the east and west parking lots at Turkey Mountain in Council District 2.
Staff said the west lot is a new concrete lot and the east lot will be converted from an old gravel lot to concrete. The additional rebar is intended to reinforce entrances and exits to better handle turning movements. Staff reported the original contract value at approximately $1,300,000 and said the change order represents about a 2.92% increase and recommended approval, saying ‘‘We believe it makes for better quality parking lots up in that area.’’
A councilor asked whether the rebar was sourced from a local supplier; staff said they would follow up on supplier details. The transcript does not record a final committee vote in the provided excerpt.