Summary
Stadium Solutions presented two grandstand options (about $540,000 for ~1,300 seats and $680,000 for ~1,500 seats) and several add-ons; the board voted to hold a special meeting to consider bleacher selection, concession facilities, electrical and plumbing, passing the motion by roll call.
Get email alerts on the Facilities Capital Projects topic
No spam. Unsubscribe anytime.
The Ambridge Area School District board heard a detailed presentation from Stadium Solutions on proposed grandstand replacements and related site work and then voted to schedule a special meeting to consider the project in full.
Martin Clubford of Stadium Solutions described two primary options: a fully closed, interlocking deck grandstand for roughly 1,300 seats at about $540,000, and a larger 1,500-seat option at about $680,000. He described optional add-ons: a black vinyl chain-link fence (quoted $2,500), riser closure around the base (about $35,000), and placing fabric and 3 inches of stone under the structure to permit storage (about $15,000). "Basically, you're looking at over the 1,300 seats, $540,000," Clubford told the board.
The vendor also addressed site details: saw-cutting and cleaning the adjacent blacktop and installing a French drain to tie into existing catch basins; he estimated saw-cut work in the packet (transcript lists a figure described as "18.05"—see clarifying details below) and described a fabrication lead time of roughly 12 weeks followed by on-site installation time.
Board members and staff pressed the vendor and the administration on permits, stamped drawings and electrical work. The record shows estimates of roughly $8,000 for drawings needed to pull electrical permits. Administration and the vendor said building-permit fees vary by municipality and that some permit-related costs are generally excluded from state-contract pricing or vendor quotes.
Because the timeline for fabrication and municipal permitting could affect the district—s ability to meet an earlier target date, a board member moved to set a special meeting dedicated to the bleachers/stadium/concession and utility items so the board could vote with full information. The motion was seconded and the board took a roll-call vote; the motion carried. The roll-call record in the transcript shows eight 'Yes' votes and one 'No' (Mister Zaggi). The board will set a date and publish required legal notice for the special meeting to consider the capital project in more detail.
Provenance: presentation begins SEG 759 and related permitting/Q&A runs through SEG 1419; motion and roll call recorded SEG 1443-1531.
Clarifying note on an ambiguous figure: the transcript lists a line described in the vendor—s packet and discussion as "18.05" for a blacktop saw cut and drainage cleanup. The raw transcript value is unclear (no currency unit or thousands separator). The article flags that figure as unclear and lists it in clarifying_details as "not specified" until the administration or vendor confirms the exact amount and units.