Valley County reviews remaining project funds, approves claims
Summary
County leaders updated the board on remaining LACFA/ARPA and road funds, discussed one outstanding Pacific West invoice and a near‑term parking‑lot budget, then approved claims and board orders by voice vote.
Get email alerts on the County Finance topic
No spam. Unsubscribe anytime.
Valley County commissioners received an update Nov. 10 on remaining project funds and approved the board claims for payment.
Speaker 1 asked for a status report on LACFA and ARPA funds and on billing from contractor Pacific West. Speaker 3 said Pacific West is essentially finished on its work but the county awaits a final signed paper from the state fire marshal for Cascade Fire Chief Steve Hall and noted only one invoice has been received so far. Speaker 1 said the contractor "will invoice this then up to the $2.50" (as reported in the meeting) and estimated there is "almost $3.50" remaining for the parking‑lot portion of the project as discussed in the session; the transcript did not clarify whether those dollar amounts represent thousands, hundreds of thousands, or another unit.
On road department funds, Speaker 1 reported what was characterized in the meeting as "a million $2.88 left and probably gonna need another 600"; the transcript language is imprecise and the exact dollar totals were not clarified during the meeting.
Later in the session, Speaker 7 moved to "approve the claims and board order claims forward" and Speaker 3 seconded the motion; the board approved the claims by voice vote.
What happens next: staff will continue to track Pacific West invoices and provide updated, itemized fund balances for LACFA, ARPA and the road department at a later meeting.