High‑school renovation advances; auditorium will close in March and music programs will relocate
Summary
District staff reported two change orders for high‑school renovations — $10,915.16 for anti‑corrosive ceiling materials for the auditorium and an estimated $47,462 for chilled‑pipe replacement in Phase 1 — and outlined phase completion dates with the auditorium scheduled to shut in March and music moving to South Lebanon Elementary.
Get email alerts on the Facilities Renovation topic
No spam. Unsubscribe anytime.
Administration gave a progress update on the Cornwall‑Lebanon High School renovation and associated stadium work.
Facilities staff said contractors discovered ceiling materials at the auditorium required corrosion‑resistant products; the district approved a change order for the general contractor for $10,915.16 to replace those materials. In the mechanical scope, North Bay Mechanical found corroded chilled piping once demolition began; the Phase‑1 replacement for identified piping is estimated at $47,462. Facilities staff explained the bid included contingency formulas for unforeseen piping work and that additional replacements could appear in older building sections as crews expose concealed systems.
Phasing and timing: Phase 1a is expected to be completed around Dec. 24 and includes the library, roughly 12–13 classrooms, the high‑school technology office and a converted restroom. Phase 1b is targeted for completion Jan. 31 and includes a multipurpose room and mechanical room. Phase 2 — which includes a science wing and the music wing near the main entrance — will begin after Christmas and overlap 1b; the auditorium is scheduled to be shut down in March. To accommodate the music program, public work sessions and some board meetings will relocate to South Lebanon Elementary beginning Jan. 5 while renovations are underway.
The administration said it contracted moving assistance and will also use staff to handle logistics during the holiday move starting Dec. 26. Board members asked about impacts to spring events; administration said the spring musical will be relocated to the middle school and other events (awards, banquets, commencement) are being rescheduled as needed.
Next steps: Facilities will continue phase‑by‑phase evaluation, monitor contingencies within the project budget, and communicate relocation plans for events and programs to affected stakeholders.