Dublin City (Regular School District) opens bids for Brazil Middle School roof; lowest base bid $753,179
Get AI-powered insights, summaries, and transcripts
Sign Up FreeSummary
District finance staff opened and read eight bids for a Brazil Middle School roof replacement. RBT Roofing submitted the lowest base bid at $753,179; bids range to $1,203,200. Bid bonds and contractor qualification statements were included for most submissions; no award was made at the opening.
The Dublin City (Regular School District) opened and read bids for a replacement roof at Brazil Middle School during a recorded bid-opening session. District finance staff confirmed multiple bid bonds and contractor qualification statements and read base bids and alternates into the record.
District treasurer/CFO announced the session, saying, "We're here today to do a bid opening for, Brazil Middle School roof," and staff proceeded to read each submission aloud. Staff identified eight responsive packages and noted at least one package lacked a proper bid form.
RBT Roofing submitted the lowest base bid at $753,179. Other base bids recorded were: Bill Jackson Roofing $797,100; O'Hara and Son Roofing $890,093; Master Construction Solutions $931,600; Riviera (transcribed once as 'Revere') Roofing Company $1,018,000; Kelly Brothers Roofing $1,145,000; and NF Mansudo and Sons $1,203,200. Several firms also offered priced alternates for specific scope items; many alternates were marked "no bid" for Alternate 1 in the read record.
Staff confirmed that bid bonds and contractor qualification statements were included with most submissions. In one instance a staff member flagged a package as not including the correct bid form and therefore nonconforming for that requirement.
The bid opening itself records submissions and documentation; it does not constitute an award. No contract award or final selection was made on the record during the opening. The record contains the bids and documentation as read; subsequent review and any evaluation, recommendation, or award will occur according to the district's procurement procedures.
Compiled list of base bids read into the record: RBT Roofing $753,179; Bill Jackson Roofing $797,100; O'Hara and Son Roofing $890,093; Master Construction Solutions $931,600; Riviera (listed once as 'Revere') Roofing Company $1,018,000; Kelly Brothers Roofing $1,145,000; NF Mansudo and Sons $1,203,200. Alternate prices and contractor qualification confirmations were noted in the record for several bidders.