County official says Coward Mill Road costs rose after phased bids, railroad and right‑of‑way work; board told phase two due April 2026

Knox County Board of Education · November 4, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

A county representative told the board Coward Mill Road costs rose because construction was phased when the school opened early, railroad work added about $1 million, and additional right‑of‑way acquisitions were required; staff said phase two completion is scheduled for April 2026.

The Knox County representative in charge of the Coward Mill Road project briefed the Board of Education during the Nov. 3 work session, explaining why the project’s price tag has increased since earlier estimates and when the district can expect the road work to finish.

Mr. Snowden told the board that the project was divided into phases after the school opened…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans