Council approves $426,129.17 appropriation for Toledo Edison work on downtown utility burial
Summary
Council approved Ordinance 1‑21‑2025 to appropriate $426,129.17 to pay Toledo Edison for undergrounding aerial facilities as part of downtown transportation improvements; administration said construction could begin in December/January pending bid results.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Council voted to appropriate $426,129.17 to compensate Toledo Edison for its portion of downtown utility relocation work tied to city transportation improvements.
Service Director Joe Shaw described the project as the final mayor/council step for the aerial‑to‑underground effort, noting earlier easements and a subordination agreement had been completed. Shaw said the utility work is the city’s largest remaining cost and that the city’s own utility project will place infrastructure in the ground before utilities transition their lines. "This is the cost that's in front of you tonight for approval," Shaw said, identifying the amount of $426,129.17 as Edison’s current billing proposal.
Shaw said the construction bid opening for the utility project had been delayed and that, if bids proceed on schedule, construction could start in December or January with roughly six months of major work planned and subsequent transfers by the utilities.
Council introduced and passed Ordinance 1‑21‑2025 as an emergency measure to authorize the mayor and finance director to accept Toledo Edison’s proposal; the motion carried on voice vote.
Next steps: Administration will finalize construction bids, coordinate the multi‑utility schedule, and begin construction once contracts are in place.