Marshfield council approves updated CIP; staff flags several project cost and funding-source changes
Summary
The council approved revisions to the 2026–2030 capital improvement plan, including reinstating airport and fairgrounds projects, shifting some items to long-term debt, and raising stormwater estimates; staff said borrowing in 2026 is larger than usual because of the police relocation project and several reconstruction projects in later years.
Get email alerts on the Capital Improvement Plan topic
No spam. Unsubscribe anytime.
City of Marshfield council members on Oct. 27 approved changes to the 2026–2030 capital improvement plan after staff outlined several project adjustments and financing shifts.
Steve (city staff) reviewed projects restored to the plan and items with revised funding sources. He said airport runway lighting (project referenced in the packet) was returned to the plan and would carry a city share of about $42,000 to long-term debt. A fuel-tank replacement project at the airport was moved to long-term debt after staff determined the airport capital fund did not have the expected balance.
Staff also described changes to street reconstruction and stormwater items. The Fifth Street reconstruction (Chestnut to Oak) line in the packet was increased to reflect recent real estate acquisition and consultant costs; staff tied that increase to the council’s recent approvals related to the project. Stormwater detention work at Brain Park was described as having a substantially higher estimate than previously shown. Steve highlighted the five-year borrowing schedule: 2026 borrowing is higher than typical largely because of a police relocation project and several state-funded reconstruction projects the city intends to accept rather than decline.
Council members asked practical questions (for example, whether cemetery lawnmower replacements are included); staff clarified that machinery and equipment replacements are determined from the machinery and equipment fund (701) and will be decided next year.
Council member Dallas moved to approve the CIP as presented with the changes and the presiding officer recorded the motion passing (no roll-call tally provided in the transcript). Staff said the detailed packet (page 8 and subsequent schedules) shows the specific project identifiers and financing tables for the five-year plan.
Next steps: the approved CIP changes will be incorporated into the revised budget that staff will publish for the Nov. 25 public hearing. Staff and council members noted some figures in the meeting were delivered from the packet and should be confirmed in the official CIP documents available with the city clerk.