Summary
Council approved $2,185,000 in plan specifications for 2026 concrete paving improvements (CIP 207175/107), and accepted vendor quotes: Sirius Computer Solutions for Cisco maintenance ($45,501.77) and Downey Drilling for Well No. 11 repair ($14,050).
Get email alerts on the Infrastructure Contracts topic
No spam. Unsubscribe anytime.
At its Nov. 3 meeting, the Columbus City Council approved plans and an estimated $2,185,000 cost for 2026 concrete paving improvements (CIP numbers 207175 and 107) and authorized advertising for bids. The engineering discussion identified the main project as the 30 Third Avenue corridor (from about 30 First Street to 30 Eighth), with additional downtown and smaller sections included.
The council also reviewed and accepted a $45,501.77 proposal from Sirius Computer Solutions LLC to renew a Cisco maintenance agreement and approved a $14,050 quote from Downey Drilling for repair, inspection and chemical treatment of Well No. 11. Each item was moved, seconded and approved by voice vote; the meeting record shows approvals by voice vote but does not list individual roll‑call tallies.
The paving project plans and specifications are on file with the engineering department; staff were authorized to advertise for bids under the stated CIP numbers. Procurement and scheduling for the vendor contracts will be handled by the appropriate city departments.