Citizen Portal
Sign In

Get AI Briefings, Transcripts & Alerts on Local & National Government Meetings — Forever.

Public Works committee approves equipment purchases, contracts and $8.9M Uchee Creek change order

Columbia County Public Works and Engineering Services Committee · October 28, 2025

Loading...

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Columbia County Public Works committee on Oct. 28 approved a large set of procurement items and contracts — including a $8.886M change order for the Uchee Creek sewer force main funded from ARPA — plus multiple equipment purchases, engineering contracts and utility agreements, all advanced by procedural consent.

Columbia County’s Public Works and Engineering Services Committee approved a broad set of purchases, engineering agreements and change orders at its Oct. 28 meeting, moving the items into consent and advancing them without recorded roll-call vote tallies in the transcript.

Resolution 25-37: Commissioner Schachter (speaker 3) introduced Resolution 25-37, which would transfer a former State Patrol post to full state ownership but adds a reversionary clause returning the land and building to the county if the property is not used as a State Patrol post. Schachter moved the item and it was seconded and advanced procedurally.

Major contracts and procurements approved or advanced by consent included: - Grasshopper mowers for Rosen Bridges: staff recommended purchase of three mowers for $52,396.23. - Stormwater vehicles: staff recommended approval of two replacement vehicles and one new vehicle for stormwater operations; the transcript’s numeric total for these three vehicles was unclear and is recorded as not specified in the transcript. - Skid steer for recreation: budgeted purchase of a skid steer at $88,900 to reduce rentals and meet increasing parks workloads. - Vermeer mini excavators: a mini excavator for special projects with a low quote recorded as $69,032.78, and a slightly larger mini excavator for the distribution department (budgeted $90,000; a low quote was referenced in the record but the transcript’s numeric text is partially unclear). - Water meters (Census): purchase recommended for $181,546.92 to rebuild inventory for the county’s automatic meter reading system; staff said the county is roughly 95% complete on a county-wide meter conversion with Jefferson Electric. - HVAC replacement at Jim Blanchard Water Treatment Plant: an independent contractor agreement to replace a nearly two-decade-old unit that cools the SCADA/operations building; three quotes were received and staff recommended the low quote (amount recorded approximately in the transcript). - Pipeline cleaning, Phase 2 (American Pipeline Solutions): sole bidder American Pipeline Solutions for $785,300 to perform sponge and ice pigging after launch/receiving stations are installed; staff reported the work should start in February and finish in February if weather cooperates. - MOU with DOT and ISM engineering: an MOU with DOT for a roundabout at Louisville Road and Columbia Road requiring relocation of a 12-inch water line (DOT estimate $403,201.80) and a separate contract with ISM for Series 44 utility drawings ($20,500). - Crown structural evaluation: structural engineering evaluation of a depression at a Halele Farm tank by Crown (manufacturer) for $35,230. - Georgia Power agreement: county to fund $114,871.48 to bring power to the Progress Drive lift station in White Oak Industrial Park with a refund mechanism if users connect within five years. - Uchee Creek Sewer Force Main change order No. 1: staff reported design omissions, additional fittings and unexpected rock/blasting and other storm-related clearing increased costs; the total change order amount was reported as $8,886,982.72 and will be paid from ARPA funds, per the staff presentation. - UV lining rehab change order (Cajun Construction): a change order covering a point repair and UV lining in Walnut Hill Subdivision totaled $96,500 to increase pipe capacity and address a failure. - Furious Ferry Road/Milliken water line abandonment: staff presented an abandonment priced at $40,534.90; inspectors will monitor excavation work while the county proceeds in the project area. - Riverwood Roundabout reconciliation: additional funding requested of $27,524.81. - GDOT and GIAP supplemental agreements: a GDOT supplemental covering $5.2 million of additional funding and a $1.5 million funding shift to Hardeman McManus Road widening; a related $1.5 million shift from Ooch Creek to the Harding/McManus project was presented with staff noting about $1 million surplus remains in the Ooch Creek project. - Pond and Company: contract for Washington Road widening design for $2,538,900 (federal 80/20 split; initial scoping task order not to exceed $25,000). - SNME geotechnical investigations: $48,000 for geotechnical work at the Savannah Rapids Pavilion funded from TAVT disaster recovery. - TriplePoint Engineering: post-closure care, maintenance and compliance contract at Baker Place Road Landfill for $466,300 ($366,300 recurring work + $100,000 for minor task orders under $25,000).

Commissioners asked operational and funding questions on several items — for example, how stormwater vehicle funds roll into fund balance, tariff impacts on meter purchases, inspection oversight for water-main abandonment work and refund mechanisms for Georgia Power reimbursement agreements. Staff responded with budget and procurement process clarifications during the presentations.

Chair (speaker 1) moved two executive-session items after the consent motions and adjourned the meeting at 9:13 a.m. The transcript does not include roll-call vote tallies; most items were advanced by unanimous procedural consent in the meeting record.