Lompoc council approves roughly $89,000 in change orders for Johns/Bridal Park restroom project

Lompoc City Council ยท November 5, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved an approximately $89,000 change order that raises the Johns/Bridal Park restroom/concession project from roughly $195,000 to about $285,000; staff said CDBG funds cover the increase, while council members questioned a roughly 45% increase in contract cost.

The Lompoc City Council voted Nov. 4 to approve an approximately $89,000 change order that increases the total contract for the Johns/Bridal Park restroom and concession project to about $2.85 million (note: transcript numeric formatting is inconsistent; staff explained the initial contract was roughly $195,000 with change orders bringing it to $285,000 and that CDBG funds were appropriated to cover the total).

Project staff told the council that the change orders occurred between May and July and were required to relocate electrical components, irrigation panels and other unforeseen site work. "There was an oversight on my part as well since the contract did not come to city council, but there were appropriations already approved through CDBG before the project," staff said.

Council members expressed concern at the magnitude of the change orders โ€” described in the record as about a 45% increase relative to the original contract price โ€” and pressed staff for improvements to procurement oversight. Project staff and accounts-payable said available CDBG funds will cover the project and any residuals will remain in CDBG accounts for future park projects.

The council approved the change order by unanimous vote, allowing the outstanding invoice to be paid and the contractor to complete final administrative closeout.

What happens next: Staff will process payment to the contractor and return to council as needed on procurement and budget process improvements.