Denton council approves amended design agreement to pursue new 30 MGD Pecan Creek plant

Denton City Council · August 5, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved a contract amendment to expand Pecan Creek water treatment planning to a new 30 MGD plant, with staff saying a new build would save an estimated $133 million compared with phased rehab and expansion; amendment passed 6‑0.

City project staff sought approval to amend a professional services agreement with Kimley‑Horn (listed in backup as Kimley/‘Kimberly Horne and Associates’) to design the chosen approach for the Pecan Creek water treatment facility. Jason Donald, water‑utilities project manager, explained the analysis comparing options: rehab and staged expansion versus constructing a new 30 MGD plant. The new‑build option was presented as both faster (roughly 2½ years quicker) and materially cheaper—staff cited a roughly $133 million lifecycle savings in the presentation.

Council voted unanimously to approve the contract amendment (adding approximately $18.8 million to bring the professional‑services total to about $33.79 million) to complete design and construction administration for the new 30 MGD facility and related systems, including UV disinfection, equalization basin and SCADA improvements. Staff said the new plant will be built adjacent to the existing site; the current plant will be decommissioned and removed after the new facility is complete.