Collegedale approves Skyboss change order after engineering error blamed on Garver

Collegedale City Commission · September 2, 2025

Summary

The commission approved a change order to fix mismatched hangar elevations at the Skyboss site, citing an aeronautical slope miscalculation attributed to engineering firm Garver; the vote drew two abstentions and commissioners said they will pursue a claim process with the firm.

The Collegedale City Commission on Sept. 2 approved a change order to correct finish-floor elevation mismatches at two hangars on the Skyboss site after staff said the original Garver design produced an excessively steep taxiway slope.

City staff told commissioners the elevation discrepancy produced about a 3.5% slope where aeronautical standards and operational safety require a more gradual grade. Because the work had been needed to maintain schedule, staff executed the repairs under the city's emergency-expenditure process and presented the change order for commission approval.

Commissioners debated liability and communications with Garver. Several members described the problem as an engineering error in Garver's original submittal; staff said the city has a claims procedure and will seek remediation from the firm while allowing the contractor to complete the work to avoid schedule delays. Commissioner House and Vice Mayor Sadler abstained from the final vote; Commissioners Baker, Johnson and Mayor Lloyd voted yes, and the motion passed.

Commissioners asked staff to compile the full cost, confirm remaining grant availability (staff noted approximately $80,000 remained in the TDOT grant for the project), and document communications with Garver so the commission can determine whether to pursue legal or contractual remedies.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source