Commissioners approve Gallatin garage settlement and crosswalk MOU, recoup temporary CO fees

Sumner County Board of Commissioners · November 12, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Sumner County approved a settlement with the City of Gallatin resolving roughly $907,496 in disputed fees by accepting $703,420.25 with a $150,000 crosswalk allocation. The board required an MOU holding Gallatin responsible for any costs above $150,000 and approved an amendment to recapture roughly $21,000 in temporary CO fees.

Sumner County commissioners approved a reconciliation with the City of Gallatin on a courthouse/parking garage project and set terms for the crosswalk construction after lengthy questioning about waived fees and temporary permit charges.

County mayor presented a spreadsheet showing fees on the Gallatin project; the amount Gallatin owed was described as about $907,496 and Gallatin agreed to a payment of $703,420.25. Under the proposal Gallatin would oversee construction of a pedestrian crosswalk and allocate $150,000 for that work, refunding any unused balance and providing receipts.

Commissioners pressed for written terms. Commissioner Becker asked for assurance that ‘‘they bear all risk’’ for cost overruns; the chair moved to approve the settlement contingent on an MOU that requires the City of Gallatin to bear any costs above the $150,000 allocation and to refund any underage.

Commissioner Klein and others objected to temporary certificate‑of‑occupancy (CO) fees tied to the project, describing them as a potential windfall (noting a roughly $3,018 quarterly charge leading to a recapture target of about $21,000). The commission voted to amend the motion to recapture the temporary CO fees and then voted to approve the main motion with the MOU contingency. The final approval was unanimous following the amendment.

The board directed the county attorney to draft contract language (MOU) to document Gallatin’s assumption of cost risk for the crosswalk and to require documentation of waived and refunded fees.