City receives update on DPS Stations 30 and 31; designs progressing toward GMP
Summary
Chief Siri and AGCM reported concept approvals and 40–50% design completion for DPS Stations 30 and 31; staff expects a GMP to be developed after design completion and tentative station completion dates in 2026 and early 2027 were given.
Get email alerts on the Dps Stations Update topic
No spam. Unsubscribe anytime.
Heath officials received a monthly design and construction briefing on Texas Department of Public Safety Stations 30 and 31. AGCM architects and the police chief presented concept plans, approved elevations, interior layouts and a project health indicator showing the design phase as "good" with the expectation it will reach "excellent" as design and procurement proceed.
Staff said design fees are roughly 40–50% complete and site plans are in development. The guaranteed maximum price (GMP) will be developed once designs are finalized; staff expects Station 31 to be completed in 2026 and Station 30 in early 2027. The council praised early coordination and cross-department collaboration and asked for continued status updates as the project moves into procurement and construction.
Council members asked why the health indicator was marked "good" rather than "excellent"; architects replied that concept design is strong and the indicator reflects outstanding tasks remaining in design and procurement prior to construction.