All Points Broadband says underground and aerial build ramps in 2026; first cabinets to light in early 2026
Summary
All Points Broadband reported progress on pole attachments and middle‑mile integration with Dominion, built the first cabinet for Fauquier 4, and said last‑mile construction will start after pending VDOT permits with service activations planned January–March 2026 in initial areas.
All Points Broadband updated the Fauquier County Board on the Virginia Telecommunications Initiative rollout and construction sequencing for the county’s fiber network.
"Overall they expect to build about 250 miles of fiber in the county. So far they've built 145 miles," said the All Points representative, who explained that Dominion Energy’s middle‑mile build is critical to providing redundancy and splice points for the last‑mile network.
All Points said…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat