Council signs off on final bills for golf-course water tank and treatment-plant electrical work

Mobridge City Council · November 13, 2025

Loading...

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Mobridge approved pay request No. 8 to Preload LLC ($206,766.45), a deducted change order for Crow River (-$24,413.80) and a $71,955 payout to Muth Electric for work at the water treatment plant; the council closed the tank project subject to one-year warranty.

The council approved multiple final payments and a deducted change order for water‑system work during its Nov. 12 meeting.

Michael Warder of Moore Engineering said pay request No. 8 to Preload LLC covers final prestressing, painting, ladder and mixer work on the new water storage tank by the golf course and requested approval of $206,766.45. The council moved, seconded and approved the pay request by roll call.

Warder also described Crow River’s change order No. 4 as a negative balancing change order for $24,413.80 to close out punch‑list items along the DOT ditch and tank area; the council approved that change order and then approved the final payout, releasing retainage and placing a one‑year warranty on the project.

Warder presented pay request No. 6 for Muth Electric for electrical work at the Northwest water treatment plant and the council approved $71,955 for conduit, wire pulling and other electrical work.

Each of these items passed by roll call with no opposing votes. Warder said the payouts complete the projects and shift them into warranty periods.