Summary

The commission closed the case for 1441 Millbrook Circle and postponed final closure of 1440 Melborough Circle and 201 East Street pending minor outstanding repairs and reinspection; staff said remaining issues were largely non‑life‑safety items.

The Housing Commission voted to close the case at 1441 Millbrook Circle after staff reported compliance or acceptable progress. A commissioner moved to close that case and the vote passed with affirmative responses from commissioners present.

For 1440 Melborough Circle, staff reported visible improvement: washing machines removed and vehicles present with paperwork for release; remaining items were mostly personal tools and yard clutter rather than immediate safety hazards. Commission discussion concluded the property was “as good as it's gonna get,” and commissioners accepted staff’s recommendation to keep the file open if new violations recur.

At 201 East Street, a property representative and staff described completed work on fire alarms and sprinklers: replaced sprinklers, painted and secured riser doors, installed a missing hydrant component and addressed smoke alarms. Staff recommended holding the item open for one more month so they could recheck a short list of outstanding items — dryer‑vent screens, missing locking caps on some AC units, trimming around hydrants, and possible storage under stairs that could block egress.

A motion was made to move the 201 East Street case to the Dec. 10 meeting for final closure pending staff reinspection; commissioners approved moving the item to December. Staff said they will re‑inspect with Brian (staff) and will not necessarily require a property representative to attend if the items are completed on site.

The commission also fielded a correspondence item asking for an update on pest control work at Myra Avenue; staff said they would follow up.