Chester council probes change orders, contamination and consultant costs on Public Works Building project
Summary
Council questioned multiple change orders for the Public Works Building, including removal of contaminated soil (manganese) and a $9,886 change order increasing Davis Construction’s contract; staff said Colliers identified contaminants but the city ratified MG Engineering for oversight because of cost and timing concerns.
During the Nov. 10 deliberative meeting, Council and Controller Joy Taylor pressed city staff about recent change orders and consultant engagements tied to the Public Works Building project.
Staff explained two discrete change orders: the first addressed removal of spoiled soil and underground storage tanks (including an isolated area with elevated manganese), and a second change order (Resolution 129) increased the Davis Construction contract by $9,886 to a new total of…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat