Somerville High tile failure traced to an out-of-spec installation; contractor completing building-wide checks
Summary
Third-party drone imaging and hands-on inspections are complete for reachable areas of Somerville High School's exterior; contractors identified a single out-of-spec installation as the root cause of a tile fall and expect a final report in early November.
Get email alerts on the Building Safety topic
No spam. Unsubscribe anytime.
City infrastructure staff updated the committee on the investigation into exterior tiles at Somerville High School after a replacement tile fell and struck a parked vehicle. No one was injured.
Staff said an outside firm conducted drone imaging and provided the team a quick-turn report that helped prioritize hands-on inspections. Contractors completed boom-lift inspections of accessible areas and were using swing-stage access to inspect the remaining zones; the full inspection was expected to be finished the week following the meeting.
Contractors reported a root cause for the tile failure: a tile panel had been installed with elongated (out-of-spec) holes in the metal rail, allowing the bottom clips to work loose over time. The installer—s representative expressed regret; contractors removed panels in multiple locations to check for similar conditions and then developed a less-invasive measuring method (approved by the manufacturer) to assess other areas.
Staff said they had involved the system manufacturer and that the installer and manufacturer were reviewing remediation options. A final report was expected in early November; staff said they would share the report with the committee.