District says ESSER/SAVE projects nearing closeout; paging system fixed, LED rebate about $74,000
Summary
District staff told the board on Oct. 27 that ESSER and SAVE construction is nearing completion but retainages and punch-list items remain; a complicated paging/fire-alarm integration required rebuilding the voice programming and is now functioning.
Get email alerts on the Facility Construction topic
No spam. Unsubscribe anytime.
District staff reported steady progress on ESSER and SAVE construction projects at the Oct. 27 board meeting, but said several closeout steps remain before all retainages can be released.
What staff said: Work across bid packages is substantially complete for several packages. The district is holding retainage on bid pack 1 through its warranty period to address any post-completion issues; the retainage is scheduled to be released in February 2026 unless warranty or insurance issues require otherwise. Bid pack 3 (electrical) is closed and paid; bid pack 2 has signage items outstanding; bid pack 4 is awaiting final documentation. Staff recommended approval of the substantial completion for the REW contract and a release of retainage for the gym roof contractor (Brookway) after they submitted required contract closeout documents and inspection reports.
Paging, fire alarm and clocks: Staff described a multi-phase conversion of paging to the building’s emergency voice (fire alarm) system to reduce costs. Because phasing occurred across construction stages, the voice-programming became corrupted and technicians ultimately had to delete and rebuild the fire-alarm voice programming, add amplifiers and replace devices to restore paging and emergency-voice functions. The district retained a minimal Bogen two-way function for office communication. The clock system was converted to radio-synchronized clocks; most clocks were replaced and now take time from a radio signal rather than wired head-end equipment.
Energy upgrades and rebate: Staff reported that LED fixture replacement is planned across interior and exterior fixtures and that Alliant provided a rebate in excess of $70,000 for energy-related upgrades tied to both ESSER and SAVE projects. Staff estimated the combined rebate at roughly $74,000.
Warranty and retainage: For the gym roof project the board reviewed warranty terms and documentation. Staff said the roof carries a manufacturer warranty reported as a 20‑year warranty (warranty issued by the manufacturer, not the contractor). With closeout documentation complete, the board approved release of retainage for Brookway Mechanical/Roofing for the gym roof package.
Why it matters: The updates affect building safety, operations and budget timing. Retainage holds protect the district during manufacturer warranty and two-year contractor warranty periods; resolving the paging system restored emergency voice capability that doubles as routine paging.