School board approves roofing, modular classroom change orders and central freezer repair contracts
Summary
The board voted to award a roofing contract, approve final change orders for two modular classroom projects and authorize a TIPS-USA cooperative contract to replace a central food-service freezer. The measures passed by voice/hand vote after staff presentations with project costs and warranty details disclosed.
Get email alerts on the Facilities Procurement topic
No spam. Unsubscribe anytime.
The Catawba County Board of Education on Oct. 27 approved a set of construction and equipment contracts and related change orders for district facilities.
Stephen Westmoreland of the districtoperations/construction and maintenance department recommended awarding a roofing contract for the transportation storage building to Conover Construction, citing the low bid of $69,930 and a two-year contractor warranty with a 20-year manufacturer product warranty. "This roof will match the previously awarded maintenance barn roof on the same material," Westmoreland said.
The board also approved final change order No. 1 for the Balls Creek Elementary mobile modular classroom project. Westmoreland reported the original approved contract was $206,945; credits of $26,369.57 reduce the final contract amount to $180,575.43. He told the board the credit and final figure during the meeting.
For the St. Stephen's Elementary mobile modular classroom project, the board approved two construction change directives (location services overage and reworking of a light pole) and a final change order that reduced the contract to $243,837.33 after credits. Westmoreland said the general contingency balance will be affected by the overages and credits discussed in the work session.
Child nutrition staff reported one of two central freezers is inoperable. The board authorized use of the TIPS-USA purchasing cooperative to contract with Curlin Way (Curlin Ray in the transcript) to remove the existing condenser and indoor evaporator, install new equipment at the same locations, and provide a one-year parts-and-labor warranty. The project cost is $106,664.51; Westmoreland said the district needs the freezer ready by January to accommodate a large incoming food shipment.
Each of these items was presented by district staff and approved by motion with no discussion noted in the public transcript. The motions were adopted by hand/voice vote; specific roll-call tallies were not recorded in the minutes provided.
The board heard timing and contingency details for each project and asked staff about contractor mobilization and schedule; Westmoreland said Conover Construction is already mobilized and that the freezer work is expected to be completed in about eight weeks.
Proper names: Catawba County Schools; Conover Construction; Curlin Way; Balls Creek Elementary School; St. Stephen's Elementary School.
What happens next: Staff will execute contracts and schedule work per the maintenance and construction plan.