Kootenai County justice building finishes under budget by roughly $2.64 million, officials report

Kootenai County Board of Commissioners · October 29, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Turner & Townsend and county staff presented a final reconciliation of the Justice Building project showing construction plus soft costs of $33,653,485 against a $35,607,527 budget, an underrun of $2,641,857. Staff said about $15,000 in remaining FF&E and finish items will roll into FY26.

Turner & Townsend project manager David Mendez told Kootenai County commissioners on Oct. 28 that the Justice Building project closed substantially under the overall budget.

"I have given you a four‑page spreadsheet that covers these items," Mendez said, and walked the board through contingencies, change orders and soft‑cost reconciliations.

Mendez and county staff reported a construction and soft‑cost total of $33,653,485 compared with a budget of $35,607,527, yielding an underrun of $2,641,857. The presentation detailed unused design and construction contingency amounts (totaling roughly $573,205) and unused allowances that created a net credit of approximately $747,200.

Jeff Fuller and Mendez described a remaining set of small FF&E and finish items — judge peepholes, a privacy lock for a men's restroom, conference‑room table modifications, attorney‑client speak‑through modifications, a replacement desk and storage racks — that together are expected to total about $15,000. County staff said those items will be carried into the FY26 budget and processed through remaining closeout work, including certified payroll audits and final billings.

Why it matters: The presentation closes a multi‑year capital project and provides transparency about contingencies, credits and owner‑carried reserves. The county reported it did not use the $1,027,000 owner‑carried contingency and that soft costs were lower than estimated by about $926,897.

What officials said: Mendez summarized line‑by‑line reconciliations, and county staff confirmed they are nearly complete with final audits and punch‑list work. "So essentially, the contractor said this is going to be a $35,000,000 project... our entire project, construction plus soft costs, came in at $33,653,000," a county speaker observed during the briefing.

Next steps: Staff will complete the remaining FF&E purchases and certified payroll audits and will present any required final change orders for formal approval in a future meeting if needed.