Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Public Works topic

No spam. Unsubscribe anytime.

Council approves $299,135.90 change order for Division Broadway restoration project

Arlington City Council · October 21, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The council approved contract change order No. 1 for the Division Broadway restoration project totaling $299,135.90. Staff said the work was needed because consultant-provided drawings omitted key elements and contained significant grade errors; the city completed much of the corrected design work in-house.

The Arlington City Council approved change order No. 1 for the Division Broadway restoration project in the amount of $299,135.90.

Public works staff member Jim Kelly told the council the change order resulted from incorrect and incomplete consultant construction drawings. "This change order...was predicated because of, we received a bad set of construction drawings from the consultant that we hired," Kelly said, and explained that the city put the design work in-house when the consultant would not update drawings.

Kelly detailed items added through the change order: significant grade breaks (as much as 18 inches from existing elevation), curbs without slope that would not drain, missing new driveways to alleys, missing ADA ramps, and missing sidewalk. He said in-house engineer Krista Stewart completed corrected drawings and the contractor and city negotiated fair pricing.

A councilmember asked about project timing; Kelly said phases 1 and 2 were done except for landscaping and striping, phase 3 work was underway and expected to be completed next Friday, and phase 4 would be a small patch at the Olympic intersection; he added, "So, November, we should be ready." The council moved to approve the change order and authorized the mayor to sign; the motion carried with no recorded opposition.

Next steps: City staff will execute the change order and proceed with remaining construction phases; the transcript does not include a revised contract completion date beyond the schedule comments in the meeting.