Mineola trustees approve multiple change orders for PTAS well treatment project

Village of Mineola Board of Trustees · August 8, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved several change orders for the PTAS well treatment project, reallocating funds between contracts and authorizing remedial work after discovery of a leaking clear well. Contractors named included Metro Group of Long Island Inc. and Benson Contracting Inc.; funding was drawn from bid allowances, leaving one allowance exhausted.

Trustees on Aug. 1 approved a string of change orders for the PTAS treatment work at multiple village wells, reallocating contract line items and authorizing repairs after the discovery of a leaking clear well.

The board approved change order No. 7 to replace the roof membrane shingles at an identified PTAS treatment well at a cost of $36,960. Mr. Palumbo said the contractor is Metro Group of Long Island Inc.; the change order reduces the value of bid item 6 and sets bid item 6 at $113,737.65 for that line item. Trustee Clark moved the resolution; the board approved the motion.

Trustees also approved change order No. 8, which shifts $50,851.50 from the general contract to the plumbing contract. Palumbo told trustees the transfer decreases the general contract’s bid item 6 and increases the plumbing contract by the same dollar amount; he described the action as a reallocation between contracts to reflect actual work responsibilities. The motion carried after a trustee motion and second.

Change order No. 9 to the plumbing contract covers the rehabilitation of a clear well that was found to be leaking. Palumbo said the work will cost $177,553 and will be performed by Benson Contracting Inc.; the funding will come from bid item 6, the allowance for additional work. He warned that after this change order “no funds remain in bid item 6.” The board approved the change order.

Separately, the board approved change order No. 1 for the Well 1 Phase 2 plumbing contract to comply with Nassau County Department of Health requests. Palumbo said the change order includes caustic piping changes, a new eyewash station and a new exhaust fan at a cost of $15,013.30; Benson Contracting Inc. is the contract vendor and the work is funded from bid item 2. Trustees voted to approve the measure.

Each resolution was presented during the public works/engineering portion of the meeting and approved by vote. The board’s actions reallocate existing bid allowances and authorize the specific repairs described above; no new revenue sources or bond authorizations were introduced during the discussion.

Palumbo and trustees did not present numerical vote tallies for individual board members on the transcript; each motion passed when the board responded “Aye” and the chair announced the motion carried.

The contracts and change orders are part of the ongoing PTAS treatment program and are recorded in village minutes and contracts files for detailed accounting and project tracking.