Summary

Sharp Property Management told the Muncie enforcement board that trash has been cleared from Southway Plaza, that roof and security issues remain, and that owners are pursuing contractor bids; the board required a site plan, contractor estimates, inspection and a 60-day plan for repairs and securing the building.

Theo Sharp of Sharp Property Management told the board that trash behind the Southway Plaza building has been cleared and that the management team is working to evaluate scope and costs for rehabbing units. Sharp said the supermarket portion of the complex “had an older roof on it, and it's in tattered” condition and that management plans to obtain quotes and a timeline for roof and exterior work.

Sharp said management has paid a retainer, has started work on exterior trash removal, and is negotiating with tenants, including a mattress store that is behind on rent. He reported plans to consider bringing businesses back into the complex and noted, "There is plans... to bring things business and, even a small convention center there as well." He described efforts to secure broken windows and to install cameras for remote monitoring.

The board asked for a site plan and a clear, 60-day plan with cost estimates and an inspection. A motion requiring a site plan, an inspection prior to the next hearing and steps to secure broken windows and the rear door carried. The manager asked for six months to complete work if possible; the board granted a 60-day deadline for the plan and an inspection to determine further continuation or other enforcement steps.

What the board directed - Submit a site plan and a list of contractor estimates for roof and structural repairs. - Secure broken windows and the rear door where the grocery store was located; install cameras if feasible to discourage dumping and trespass. - Schedule and obtain an inspection with the building commissioner’s office before the next hearing and report progress at the follow-up date.

Why it matters Southway Plaza occupies a commercial block in Muncie with visible signs of deferred maintenance and security vulnerabilities; the board’s requirements are intended to accelerate remediation, protect neighboring properties from dumping and trespass, and provide a clearer path for re-occupancy or redevelopment.

Next steps The board continued the case for 60 days and expects a site plan, inspection report and contractor estimates at the next hearing. If work is inspected and signed off before the return date, owners may not need to appear.