Council authorizes change order for Baker View fire repairs, adds estimated $12,345 for electrical work
Summary
Parks & Rec director presented a post-fire repair change order for Baker View; council authorized the mayor to execute a change order adding an Integrity Electric estimate of $12,345 to the original Scott Wall Construction contract.
Get email alerts on the Public Works Contracts topic
No spam. Unsubscribe anytime.
Jennifer Burner, Mount Vernon’s parks and recreation director, briefed the council on a post‑fire restoration project at Baker View that uncovered additional electrical damage not included in the original contract.
Burner said the city selected Scott Wall Construction as the low bidder for the base restoration work. She told council the original Scott Wall contract as presented in the packet was $68,229 (without tax) and that Integrity Electric estimated the additional electrical work at $12,345. Staff recommended the council authorize the mayor to execute a change order to address the wiring discovered in the restroom ceiling.
Council member VanderStoop moved to authorize the mayor to execute the change order and Council member Molineux seconded the motion. Mayor pro tem called for the vote and announced the motion passed with ayes recorded.
Why it matters: The change order completes necessary repairs discovered during restoration of a city facility damaged by fire in July 2024. City staff provided the scope of work and supporting estimates in the meeting packet.
Numbers and precision: The figures presented at the meeting were the original contract amount ($68,229) and the estimated additional electrical work ($12,345), which together bring the contract to about $80,574 before taxes or other administrative fees; the packet includes scope and the Integrity Electric estimate. Council authorized staff to proceed with the change order.
Next steps: Staff will execute the change order consistent with the packet authorization and complete the electrical repairs at Baker View.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.