District reports pool liner finished but boilers still pending; small cost revision noted

Weston County School Board · November 14, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Facilities staff reported the pool liner installation is complete and crews are filling the pool, but boilers have not arrived; a $9,400 contract revision covered gutter welding from pinhole leaks and project costs remain under the not-to-exceed budget.

District facilities staff told the board that the pool liner work has finished and crews are preparing the pool, but heating cannot begin while boiler contractors remain outstanding.

"The liner guys are done. They packed up, left today," the facilities lead said, reporting that the welder finished earlier and that the project remains on track for a scheduled opening in early December once boilers arrive. He noted a contract revision of $9,400 after crews discovered pinhole leaks in gutters requiring extra welding, but emphasized work stayed under the project's 'do not exceed' budget amount.

Board members praised the contractor effort and long work hours. Facilities staff said the welding and liner work improved overall conditions but reiterated that the pool cannot be heated or chemically balanced until boilers are installed.

No additional appropriation was recorded in open session; staff characterized the cost change as a revision within the allowed contract ceiling and said they would proceed once boiler work is completed.