Council approves GMP #1 ($1.078M) for sewer relocation tied to new city hall/justice center; one abstention

City of Taylor City Council · November 13, 2025

Loading...

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved Guaranteed Maximum Price (GMP) No. 1 with Bartlett Cocke for the 2nd Street sewer relocation ($1,078,066, base scope $875,000 plus allowances/contingency) to allow the city hall/justice center project to proceed; council recorded one abstention.

Council approved GMP No. 1 with Bartlett Cocke to relocate a wastewater sewer main under 2nd Street, a precondition for construction of the new city hall/justice center.

Project leads from HDR and Bartlett Cocke explained the procurement strategy: splitting the work into two GMP packages lets the sewer relocation begin now while design for the main building finishes. The base scope for the utility relocation was presented as $875,000 with allowances and contingencies (for potholing and utility conflict resolution) that bring GMP 1 to $1,078,066; the staff said the council had budgeted $1,650,000 for this item and the GMP is within that budget envelope.

Mr. Walker and the construction team said the relocation remains a gravity flow solution, will replace an undersized alley line, and is scheduled to finish in March to align with the broader site's construction schedule. A local business owner raised concerns about losing access from the closure of 2nd Street; staff replied that changing the site layout now would be costly and that the design and right‑of‑way work are well advanced.

A motion to approve GMP No. 1 passed; council recorded an abstention. Staff said the notice to proceed will be issued so utility work can start as soon as permitting and coordination are complete.

Next steps: staff will issue notice to proceed and return with GMP No. 2 (building package) for review once construction documents and bids are complete.