Glendora approves $2.09 million traffic signal upgrade and $376,085 stormwater master plan

Glendora City Council · November 17, 2025

Get AI-powered insights, summaries, and transcripts

Subscribe
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The council awarded a $2,087,197 contract for traffic signal modifications at several Route 66 and Gladstone intersections and approved a $376,085 stormwater master plan contract to Kraft Water Engineering, authorizing 10% contingency and related appropriations.

The Glendora City Council approved two infrastructure contracts on Nov. 12: an HSIP‑funded traffic signal modification contract to Select Electric, Inc. for $2,087,197 and a professional services agreement with Kraft Water Engineering for a stormwater master plan not to exceed $376,085 (including contingency).

Civil Engineering Assistant Abel Paglias described the traffic signal package — which includes installing protected left‑turn phases at six intersections, converting pedestal signals to mast arms at two, adding high‑visibility crosswalks, upgraded lighting and ADA curb ramps — and recommended Select Electric as the lowest responsive bidder (engineer’s estimate $2,190,075; bids ranged up to $2,580,236). The council authorized change orders up to 10% and a tentative notice‑to‑proceed of Dec. 8, 2025, with construction beginning Jan. 5, 2026, and about 270 calendar days of work.

Environmental Services Analyst Stephanie Ryan presented the stormwater master plan scope: field inspections, CCTV, H&H modeling, a GIS‑based inventory and an interactive web map to identify projects and funding opportunities. Kraft Water Engineering was the low, responsive firm after scope alignment; staff requested a $126,085 supplemental appropriation from Measure W funds to fully fund the $376,085 total. Council approved both measures 5‑0.

Both items include contingency budgets and delegated authority for the public works director and city manager to execute contracts and limited change orders.