Lee's Summit North HVAC replacement to be funded by bond; equipment cost and implementation timeline presented
Summary
Facilities staff said replacing three rooftop HVAC units at Lee's Summit North will likely cost about $7.3 million total (installation plus equipment), with equipment purchase listed near $4.148 million; work is expected to be installed over summers 2026 and 2027 and will be funded from the 2025 bond program.
Mr. Gorrell presented planned mechanical upgrades at Lee's Summit North, telling the committee the school still uses original rooftop equipment more than 30 years old. Engineering review and cooperative purchasing led staff to recommend replacing the three large units with like-for-like, air-cooled systems rather than converting to a different platform; staff cited structural and ductwork…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat