Board gets timeline for Itubia and other downtown street projects; AEP pole and private sign pose alignment challenge
Summary
City staff told the board the Itubia Street project should move to contract in 2–3 weeks with a mid-December preconstruction meeting. On Zaragoza Street, a private Payless sign encroaches on AEP lines; staff said the city lacks a clear ordinance to force removal and will ask the utility and property owner to negotiate.
City staff reported progress on multiple downtown street projects and flagged a utility alignment issue that could alter a planned curb-to-curb design.
"We anticipate 2 to 3 weeks to get that whole contract received... Mid December is where we're anticipating to have a pre construction meeting," said Eduardo De Los Santos, city engineer, updating the board on the Itubia Street improvements. He told the board the contractor has been resolving bonding matters and the city expects to receive executed contract documents and a schedule once bonding and paperwork are complete. Staff said the contractor and city will…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat