Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Tolleson Aquatic Center topic
No spam. Unsubscribe anytime.
Smyrna awards $16.23M contract to build Tolleson Aquatic Center, opening targeted May 2027
Summary
The council authorized a contract award of $16,228,529.69 to Reeves Young LLC to build the Tolleson Aquatic Center, with substantial completion by March 2027 and an opening target of May 2027.
Get email alerts on the Tolleson Aquatic Center topic
No spam. Unsubscribe anytime.
Smyrna Mayor and Council approved awarding RFP 26‑002 for the Tolleson Aquatic Center to Reeves Young LLC for a contract amount reported as $16,228,529.69. City staff said five firms submitted bids, one was rejected as non‑responsive, and consultant Corey Engineering recommended Reeves Young as the lowest responsible and responsive bidder.
Staff reported an engineer’s estimate of about $18 million and described the selected bid as competitive. The contract includes a schedule to reach substantial completion by March 2027 and a target opening of May 2027. Council members expressed enthusiasm for the design and the competitive bidding results, noting that the bid outcome suggested clear specification of the project requirements.
The contract award passed unanimously, 7-0. Staff said they set an opening deadline of May 1, 2027, and that the contractor’s schedule calls for substantial completion in March 2027. The council did not discuss financing details in depth during the vote; the staff presentation framed the award as within the project budget established during procurement.
Quote from staff: "We had an engineer's estimate of 18,000,000 and the recommendation for Reeves Young… for the contract amount of $16,228,529.69," the Community Development representative reported.
Next steps: contract execution and preconstruction scheduling; staff will monitor construction milestones and report progress to council as required under city procurement policies.