Council approves $10.4M budget amendment and GMP for Hermosillo Park rehabilitation

Norwalk City Council · November 19, 2025

Loading...

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The council authorized a $10,404,164 budget amendment and approved a $49,631,712 design–build GMP with AS Construction for the Hermosillo Park rehabilitation and stormwater capture project after securing additional Measure W funding to cover a budget shortfall.

The Norwalk City Council approved a budget amendment and awarded a guaranteed maximum price for the Hermosillo Park Rehabilitation and Stormwater Capture project. Staff and the design–build team presented the project concept — including new synthetic fields, a community center, amphitheater, playground, expanded parking and an underground infiltration system — and explained a cost increase since initial planning.

At 65% design stage, the design–build cost estimate exceeded the project budget by roughly 73 percent. City staff and the design–build team conducted value engineering and pursued additional county Measure W funding; the Los Angeles County Board of Supervisors approved an additional $9.9 million. With the supplemental funding, staff reported the project is fully funded at $51,432,600.

Council approved resolution 25-56 to amend the FY 2025–26 budget by $10,404,164 for construction and authorized the city manager to execute a design–build GMP with AS Construction in the amount of $49,631,712, with standard conditions requiring budget availability for future amendments. Staff said the project team will continue to coordinate technical design and construction sequencing and thanked county partners for the Measure W allocation.

The council voted in favor of the staff recommendation.