Engineering team narrows Snoqualmie Valley Health lift station alternatives to an additional wet well; design approval expected in January
Summary
Project engineer said the alternatives analysis for the Snoqualmie Valley Health lift station has effectively narrowed to a single option — adding a wet well — with a cost estimate expected before Thanksgiving and a return to council in January to request approval to proceed to full design.
Get email alerts on the Wastewater Infrastructure topic
No spam. Unsubscribe anytime.
Patrick Fry, project engineer, told the Parks and Public Works Committee the technical memorandum on alternatives for the Snoqualmie Valley Health lift station has narrowed to one preferred option: an additional wet well. Fry said the memo and a cost estimate are expected by the end of the week (before Thanksgiving), with staff planning to use December for internal review and return to council in January to request approval to move into full design.
Fry said the hospital has received intermittent updates but that staff are not holding regular meetings with the hospital because the project is still in its planning phase. The narrowed alternative reduces design options the city must evaluate and should streamline the January presentation for council consideration.
Next steps: staff expect to present the full design request to council in January after completing the technical memo and cost estimate.