Council awards McLennan (Lake & Spruce) bridge repairs contract to Dunnet Bay Construction

Lake Forest City Council · November 18, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved awarding the McLennan (Lake and Spruce) bridge repairs contract to Dunnet Bay Construction for $1,976,924 with a $198,076 contingency (total $2,175,000) and approved a structural-engineering services agreement for $74,431 (plus $5,575 contingency) for a total of $80,000; the motion passed 8–0.

Public Works presented the McLennan (Lake & Spruce) bridge repairs project—scope includes deck and railing replacement, spot steel repairs, slope stabilization and ravine restoration—and recommended awarding the construction contract to low bidder Dunnet Bay Construction for $1,976,924 with a contingency of $198,076 (total project cost $2,175,000). The council also approved structural engineering construction-assistance services with Wiss, Janney, Elstner Associates for $74,431 plus contingency $5,575 (total $80,000). The council approved both by roll-call vote (8–0).

The project is scheduled to begin in late March with completion anticipated in mid-September; the work will require full road closures for the duration, and staff will hold an open house to discuss both bridge projects on Dec. 4 at Gordon Center.