Village reports progress on Leahy storm project; backyard boring to begin
Summary
Staff reported the Leahy stormwater project has completed major excavation and storm structure installation and that the contractor's backyard boring work will start the next day; a few properties with improper sump ties were identified and will be corrected with Aqua's involvement.
Get email alerts on the Storm Infrastructure topic
No spam. Unsubscribe anytime.
Village staff provided an update on the Leahy storm project, saying crews have completed much of the excavation and installed storm structures and connections.
Project lead Kim said the contractor will begin backyard boring the following day. Staff reported they have not received resident complaints about the project so far. During a review of existing connections, crews found a few properties where storm sump lines tied into sanitary sewer lines; staff are documenting addresses and have notified Aqua to manage reconnections.
Kim said the contractor has logged notes on existing utility connections and will make the required reconnections. No changes to schedule or budget were reported during the update.