Board approves $74,007.31 pay application for transfer station; Main Street largely complete

Board of Public Works and Safety · November 19, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff presented and the board approved pay application No. 3 for the Transfer Station modernization project ($74,007.31), leaving about $227,000 on the contract; staff also reported that Main Street paving, striping and bump-outs are complete with plantings and final concrete work remaining.

City staff presented pay application No. 3 for the Transfer Station modernization (TSO) on Nov. 18 and asked the board to approve a payment of $74,007.31. A staff presenter said the contract is about 80% complete and that the payment would leave roughly $227,000 remaining on the contract, including retainage and a small approved project increase. The board voted to approve the application by voice vote.

The board also heard a Main Street construction update: staff said the road is open, asphalt and striping are finished in the completed sections, bump-outs at intersections are installed and plant materials and minor curb work remain. “I think the new bump outs ... are fabulous and much safer for people crossing the street,” a staff member said, praising contractor All Star for meeting a challenging schedule.

Board members noted remaining punch-list items and that the project team will perform a final walkthrough before winter. Staff said additional 2026 projects are in planning stages.