CRA moves Dyson Plaza change order and outlines legacy home rehab pilot
Summary
The Community Redevelopment Agency authorized a change order to finish Dyson Plaza shell work and staff described a CRA-funded legacy home rehabilitation pilot that received 34 applications and is supporting four homes in construction with up to $50,000 per home in funding.
Get email alerts on the Cra Projects topic
No spam. Unsubscribe anytime.
The Community Redevelopment Agency and city staff briefed the commission on progress downtown and the CRA-funded legacy home rehabilitation pilot in historic East Winter Garden.
CRA staff said Dyson Plaza shell construction is roughly 94% complete; outstanding items include an underground three-phase electrical connection and an exterior awning. Staff reported a Duke Energy cost of about $43,755.59 for the electrical connection and an awning quote of $14,299, and recommended a change order to complete the work. The CRA advisory board recommended approval by a 5–2 vote, and the commission authorized the city manager to execute the change order.
Staff also described a legacy-home rehabilitation pilot administered with Rebuild Together Central Greater Florida and coordinated with '1 Winter Garden.' The pilot targeted an initial cohort of four homes to test processes before a larger rollout, with staff reporting 34 total applications received, 20 under review, 11 preapproved and four homes currently under construction. Pilot budgets are approximately up to $50,000 per home for interior and exterior repairs, ADA improvements and health-and-safety work.
Staff said the pilot will inform refinements to application processes and partnerships and that the CRA intends to continue outreach and monitoring as the pilot homes are completed.